Updates

No Photo

Significant Reconstruction for Hampshire Street!

The nearly ½ mile stretch of Hampshire Street from Turner Street to Gamage Avenue is being rebuilt by St. Laurent & Son this summer with completion planned for late fall.  This is a full depth reconstruction with removal of old pavement and…

Read More

No Photo

Over a Half Mile of Pipe to be Replaced!

St Laurent and Son recently won the bid to replace over 2,900 feet of cast iron water main pipe on Brault Street, Belleview Street and Blanchette Street between Central Avenue and East Avenue in Lewiston.  The plan calls for thirty-eight…

Read More

No Photo

Get Your Loam, Stone and Aggregate Delivery on Time for Your Memorial Day Weekend Project

Avoid disappointment this Memorial Day weekend. Call now to insure loam, stone or aggregates are delivered before the weekend, so you can complete your Memorial Day weekend projects.  We recommend delivery this Monday, Tuesday and Wednesday…

Read More

No Photo

ANOTHER REASON TO WORK FOR A GREAT COMPANY!

  St. Laurent & Son of Lewiston, Maine are not waiting for an act of Congress to address health care. Ownership will now pay 100% of employee health insurance premiums!  “Health insurance is so important to employees and their families…

Read More

No Photo

Maxwell Road Bridge Repairs – Sabattus, ME.

St. Laurent & Son is working as a subcontractor for Reed & Reed, Inc. to replace the existing one lane Maxwell Road Bridge. The bridge is over the Maine Turnpike in Sabattus. It has been closed since April 3, 2017 and will not open again until…

Read More

No Photo

Prep Your Driveway for Winter with Crushed Gravel

Be sure your crushed gravel driveway is ready for winter’s freezes and thaws and the early spring rain that follow.  There’s nothing worse than driving in the ruts and valleys your driveway can become.  Pick up your crushed gravel or have it…

Read More

No Photo

Commercial Property Owners and Managers: Are You Responsible for Your Property’s Snow Removal? 

Get it done professionally by the St. Laurent & Son “Snow Team”.  You won’t have to worry about whether or not the lot will be clear when you come in to work.  Our operators get there early and do everything possible to get your lot clean,…

Read More

No Photo

ReSeed Your Lawn with Loam from St Laurent & Son

It’s been a hot, dry summer and it’s time to rebuild your lawn.  You can still plant lawn seed now and have it ready for spring, if you do it right away.  The overnight moisture and cooler daytime temperatures is great for germination.  St…

Read More

VIP

St. Laurent & Son is doing a total parking lot reconstruction, which includes the addition of 81 new parking spaces at the VIP Tire and Service Support Center on Lexington Avenue in Lewiston. When complete a total of 115 spaces will be…

Read More

No Photo

Farwell School Addition

Farwell School Lewiston, Maine St Laurent and Son are excavating and installing concrete frost walls, sewer lines and drain lines for the Farwell School Addition in Lewiston.  In addition, St Laurent and Son will excavate and install a…

Read More

No Photo

Middle Street Substation

Middle Street, Lewiston, Maine St Laurent and Son is providing the excavation and installation of retaining walls, ductbanks, manholes, concrete footers and foundations, for a Central Maine Power electrical substation on Middle Street…

Read More

No Photo

Wastewater Collection System and Pumping Stations

Route 121 King Street, Oxford, Maine St Laurent and Son are installing over 21,000 liner feet of pipe for a new gravity sanitary sewer collection piping system in Oxford, Maine.  In addition, they will install two pump stations and a…

Read More

No Photo

Water Transmission System Improvement

Huston Road and Dyer Road Water, Gorham, Maine St Laurent and Son are excavating and installing over 8,000 linear feet of pipe for the Portland Water District.  The work will extend water transmission mains on Huston and Dyer Roads in …

Read More

No Photo

Pierce Place Redevelopment

Pierce and Bartlett Streets, Lewiston, Maine St. Laurent and Son are providing site work for a three building, 29-unit project for Pierce Place Associates.  Work includes excavation, concrete foundation, water, sewer and drain lines.  In…

Read More

No Photo

Spring Projects

Homeowners, are you looking for screened sand for the sandbox you promised the kids?  Or, maybe you need our nutrient rich loam for your garden, garden boxes, or flowerbed?  Or maybe you need crushed stone or gravel to manage drainage or…

Read More

No Photo

Reclaimed and Recycled Asphalt, Brick and Concrete

Did you know St. Laurent & Son has recycled products like 2” and 4”crushed concrete or ¾” reclaimed asphalt, and recycled bricks?  Not only are we doing our part for the environment but these items are cost-effective! Crushed concrete…

Read More

No Photo

GET YOUR AGGREGATES HERE!

It’s been an open winter here in Maine. We’re seeing familiar faces as our good friends, the landscapers and excavation contractors of Central Maine pick up material, here at the St. Laurent and Son gravel pit.  It’s the best place to get gravel,…

Read More

No Photo

Riverside Drive Project- Auburn

St. Laurent & Son will be starting on the Riverside Drive project in Auburn, ME after Memorial Day.  The project consists of replacing storm drain and reconstruction of parts of the road.  During the project traffic on Riverside Drive will be…

Read More

No Photo

Posted Roads

Each spring, MaineDOT evaluates potential damage to State and State-Aid highways, and determines whether weight restrictions should be imposed to prevent damage due to freeze/thaw action. Many municipalities undertake similar evaluations and…

Read More

Androscoggin River Trail Construction

On this project we did the actual construction of the trail.  We started with tree clearing and finished with paving and landscaping.  This project was the creation of a 1.78 mile recreational trail for pedestrian and bicycle traffic.  The…

Read More

21 - 40 of 58 items | 3 pages